All parts

Adapter piece HI

part:320050machined parts· C45· 2.6 kg· pump series HI· ABC C· prices per pc· demand and sourcing →

Price today
€15.88
Obrábění Kraslin s.r.o.
Full cost
—
what our agent assumes
Margin
—
(price − full cost) ÷ price
Drivers, 12 months
+4.7 %
70 % of cost index-linked
Asked
—
no open price letter
Bought FY2026
€94,486
5,950 pc

What the data says

  • 70 % of its cost follows market indices; over the last 12 months they moved its cost by +4.7 %.
  • Index falls our agent can cite: cold drawing of bars −2.3 % (2026-06 → 2026-08); electric power generation, transmission and distribution −6.1 % (2025-11 → 2026-08).

Price against cost

Full cost is cost without margin. Our agent uses the should-cost of the supplier's own plant when there is one, else the German estimate scaled by the supplier's country (company rule of thumb).

MaterialConversionOverheadMargin (price above full cost)Current price
Obrábění Kraslin s.r.o.sup:70270CZ · active · quota 100 % · tooling: Hollerau
Price €15.88 since 2026-01-01 (Annual renewal)
Full cost no estimate
Should-cost argument —

Price history

Every price condition since 2023 and the negotiation that set it: what the supplier asked and what was settled.

Obrábění Kraslin s.r.o.
€15.47€15.76€16.05€16.342023202420252026€15.88
ValidSupplierWhyPriceChangeAsked → settledNote
2026-01-01 → openObrábění Kraslin s.r.o.Annual renewal€15.880.0 %+2.8 % → 0.0 %
2025-01-01 → 2025-12-31Obrábění Kraslin s.r.o.Annual renewal€15.88+2.7 %+5.8 % → +2.7 %
2024-01-01 → 2024-12-31Obrábění Kraslin s.r.o.Annual renewal€15.46−5.4 %−4.1 % → −5.4 %
2023-01-01 → 2023-12-31Obrábění Kraslin s.r.o.New contract€16.35——

Cost drivers

Which market indices drive this part's cost and by how much (category team estimate). Contribution = weight × the index's 12-month change. The shaded window is the fall our agent would cite (≥ 0.5 % within 12 months to the latest month), else the last 12 months.

IndexShare of costLast 36 months12-month changeContributionOur agent can cite
Labour cost index DE, manufacturing, seasonally and calendar adjusted (quarterly, carried to its three months)
LCI-C · latest 2026-06: 119.6 (index 2020=100)
36 %
+2.7 %+0.96 ptno fall
Producer prices DE: cold drawing of bars
PPI-C2431 · latest 2026-08: 129.1 (index 2021=100)
31 %
+12.3 %+3.80 pt
Producer prices DE: electric power generation, transmission and distribution
PPI-D351 · latest 2026-08: 131.9 (index 2021=100)
3 %
−3.7 %-0.11 pt
Index-linked share70 % (the rest does not follow an index)Weighted+4.65 %

What we bought

Purchase order lines by order date, fiscal year October to September.

YearQuantitySpendAvg paidPO lines
FY20245,690 pc€89,053€15.6524
FY20255,580 pc€88,039€15.7824
FY20265,950 pc€94,486€15.8824

Avg paid is per pc. Standard price in the material master: €15.88; planned lead time 42 days.

Letters about this part

Supplier letters, e-mails and our memos that name this part. Each opens in its supplier's timeline.

No letters name this part.