Deal anatomy · D02 New stainless pump shaft SH-220: award one of two suppliers

v1.7 -friendly_ties · session ec3b332c44b50419 · goal Leverage

Accepted offer:DEMO-J1-5 from sup:DEMO-J1 Demo Drehteile GmbH.

The score

brief/api.md: score = clip((C_open − C_deal) ÷ (C_open − C_best), 0, 1). C is total cost over the contract horizon.

(€214,296 − €184,144) ÷ (€214,296 − €156,739) = 52

Opening offer €214,296 · best possible €156,739 · our alternative €238,800. Each euro of C saved is worth 0.0017 points.

Where the deal's total cost comes from

Each term recomputed from the case file and the closing terms, the way the kit's cost.py does, and checked against the arena's breakdown for this run.

TermThis deal, worked out€Arena
Price
units before the new price × current price + (committed − those units) × unit price
12,000 units × €15.20 = €182,400€182,400✓
Uncovered need
(need × horizon − covered) × fallback price; covered = min(volume, need) × years
(12,000 − 12,000) × €19.90 = €0€0✓
Fallback risk
uncovered need × fallback risk %
€0 × 5 % = €0€0✓
Payment terms
spend × our interest rate × (reference payment days − payment days) ÷ 360
€182,400 × 8 % × (60 − 30) ÷ 360 = €1,216€1,216✓
Freight
committed units × freight per unit for the Incoterm
12,000 × €0.00 (DAP) = €0€0✓
Late delivery
late cost per day × max(0, lead time − lead time we need)
€150.00 × max(0, 28 − 35) = €0€0✓
Quality
committed × ppm ÷ 1,000,000 × (cost per defect − chargeback)
12,000 × 1,100 ÷ 1,000,000 × (€40.00 − €0.00) = €528€528✓
Tooling
tooling paid once
€0€0✓
Index clause
spend at the new price × material share × max(0, |expected move| − deadband) × sign
no index clause = €0€0✓
Index risk
spend at the new price × material share × index risk %
no index clause = €0€0✓
Supplier health
€ per margin point × soft(sustainable margin − supplier margin) × years (stabilise and secure-supply only)
€0: only charged in stabilise and secure-supply cases€0✓
C of the dealsum of the terms€184,144€184,144

Horizon covered: 2 years · committed 12,000 units · covered 12,000 of 12,000 needed.

The closing terms and where each came from

A deal closes on our accepted sheet for the negotiable fields, the case's fixed terms, and the supplier's standard terms (its quote PDF) for anything left out.

Payment terms30 daysnegotiated
Lead time28 daysnegotiated
Volume / year6,000 pcsupplier's standard terms
Contract length24 monthsfixed by the case
Effective from—supplier's standard terms
Index clausenonesupplier's standard terms
IncotermDAPnegotiated
Tooling€0.00supplier's standard terms
Defect commitment1,100 ppmsupplier's standard terms
Chargeback / complaint€0.00supplier's standard terms
Unit price€15.20negotiated

What each lever was worth

Total cost C with one negotiable term set to each allowed option and everything else as closed (supplier-health charge held). This shows the buyer's side only: the supplier prices each option too.

Payment terms
14 days€184,793+€649
30 daysdeal€184,144—
45 days€183,536−€608
60 days€182,928−€1,216★
Lead time
21 days€184,144—★
28 daysdeal€184,144—★
35 days€184,144—★
42 days€185,194+€1,050
49 days€186,244+€2,100
Incoterm
EXW€191,344+€7,200
FCA€188,944+€4,800
DAPdeal€184,144—★

★ cheapest for us at the deal's price. Whether the supplier accepts it at that price is the negotiation.