Framework agreement · Blechtechnik Aichbauer GmbH
ctr:4600070310sup:703102025-07-01 → 2027-06-30· fixed per year
part:330010 Base frame HN 50/65, welded, paintedWhat the record says
- Runs to 2027-06-30 and renews unless terminated with 90 days' notice: the last day to act is 2027-04-01 (183 days after the data date).
- Prices are fixed per calendar year. A change for 2027 needed notice by 2026-10-02 (
ctr:4600070310#3.1). A price letter that gives less notice can be cited against the contract; the arena checks the letter's days against the clause's. - Delivered 63 % on time in the last 12 months (target 95 %; 63 % against its own confirmed dates), typically 9 days late when late. Citable:
sc:70310@2026Q3(the arena checks the mean on-time % of the cited scorecards). - 7 supplier-caused complaints in the last 12 months (€750 recharged at the €150 flat fee).
- We paid 89.3 % of its invoices late, 5.8 days after the due date on average (worst 17). The supplier has a fair complaint here; paying on time, or earlier, is something we can offer in exchange for price.
Clauses
The contract text, clause by clause. Notes compare it with company policy (60 days net, DAP, 95 % on time, €150 per complaint).
Subject: supply of Base frame HN 50/65, welded, painted.
Prices as per the price annex, fixed for each calendar year. Changes require written notice of at least 90 days before the end of the calendar year.
Payment: 45 days net.
Shorter than our standard 60 days net: we pay 15 days earlier than policy.
Delivery DAP; standard lead time 21 days from order.
The quality agreement applies: on-time delivery target 95 %, flat fee of EUR 150 per supplier-caused complaint.
Valid from 2025-07-01 to 2027-06-30; extends by 12 months unless terminated with 90 days' notice.
Delivery
Each goods receipt against its order line's requested date. On time = posted between 5 days early and 2 days late (scorecard method); partial deliveries count separately.
Against its own first confirmed dates: 63 % on time. Since 2023-10: 72 order lines, 7 rush and 4 changed orders, 2 still open, 1 ordered at an outdated price.
Quality
Quality notifications (qn:). Supplier-caused complaints are recharged at the €150 flat fee; an 8D report is due within 60 days.
Median 72 days to close; 13 closed after 60 days; 1 open, of which 0 overdue. 49 parts returned in total; €1,650 recharged.
| Notification | Part | Defect | Qty | Cause | 8D |
|---|---|---|---|---|---|
| qn:20005001 2026-08-24 | part:330010 Base frame HN 50/65, welded, painted | leakage at test | 3 | supplier | open |
| qn:20004974 2026-07-15 | part:330010 Base frame HN 50/65, welded, painted | surface damage | 7 | supplier | 68 d |
| qn:20004913 2026-05-06 | part:330010 Base frame HN 50/65, welded, painted | surface damage | 8 | supplier | 103 d |
| qn:20004856 2026-03-18 | part:330010 Base frame HN 50/65, welded, painted | missing marking | 5 | supplier | 82 d |
| qn:20004827 2026-02-20 | part:330010 Base frame HN 50/65, welded, painted | leakage at test | 8 | supplier | 37 d |
| qn:20004801 2026-01-22 | part:330010 Base frame HN 50/65, welded, painted | coating defect | 1 | supplier | 90 d |
| qn:20004785 2026-01-06 | part:330010 Base frame HN 50/65, welded, painted | porosity | 3 | supplier | 59 d |
| qn:20004594 2025-07-05 | part:330010 Base frame HN 50/65, welded, painted | burr / sharp edge | 3 | supplier | 65 d |
| qn:20004573 2025-06-20 | part:330010 Base frame HN 50/65, welded, painted | burr / sharp edge | 5 | supplier | 76 d |
| qn:20004422 2025-01-22 | part:330010 Base frame HN 50/65, welded, painted | missing marking | 1 | supplier | 76 d |
| qn:20004397 2025-01-04 | part:330010 Base frame HN 50/65, welded, painted | coating defect | 1 | supplier | 60 d |
| qn:20004355 2024-11-28 | part:330010 Base frame HN 50/65, welded, painted | burr / sharp edge | 2 | supplier | 52 d |
The 12 most recent notifications. The scorecards on the supplier page give the rolling ppm.
Our payments
Invoices (inv:) against their due date. This is our side of the relationship: suppliers notice when we pay late.
Invoice terms: 45 days. 4 invoices unpaid at the data date.
Cash discount: none agreed.
By fiscal year
October to September.
| Year | Invoiced | Invoices | Paid late | Avg days late | Complaints | Recharged |
|---|---|---|---|---|---|---|
| FY2024 | €696,318 | 20 | 100 % | 5.6 | 7 | €450 |
| FY2025 | €874,523 | 28 | 96.4 % | 6.5 | 6 | €450 |
| FY2026 | €851,190 | 28 | 89.3 % | 5.8 | 7 | €750 |