Framework agreement · Wälzhammer Präzision GmbH
ctr:4600070280sup:702802024-01-01 → 2026-12-31· fixed per year
part:320011 Pump shaft HN 32 mmWhat the record says
- Runs to 2026-12-31 and renews unless terminated with 90 days' notice: the last day to act is 2026-10-02 (2 days after the data date).
- Prices are fixed per calendar year. A change for 2027 needed notice by 2026-10-02 (
ctr:4600070280#3.1). A price letter that gives less notice can be cited against the contract; the arena checks the letter's days against the clause's. - Delivered 88.9 % on time in the last 12 months (target 95 %; 88.9 % against its own confirmed dates), typically 12 days late when late. Citable:
sc:70280@2026Q3(the arena checks the mean on-time % of the cited scorecards). - 3 supplier-caused complaints in the last 12 months (€300 recharged at the €150 flat fee).
- We took 7 cash discounts after the 10-day discount period (€2,085): the supplier can claim that back.
Clauses
The contract text, clause by clause. Notes compare it with company policy (60 days net, DAP, 95 % on time, €150 per complaint).
Subject: supply of Pump shaft HN 32 mm.
Prices as per the price annex, fixed for each calendar year. Changes require written notice of at least 90 days before the end of the calendar year.
Payment: 30 days net, 3 % discount within 10 days.
Shorter than our standard 60 days net: we pay 30 days earlier than policy.
Delivery EXW; standard lead time 28 days from order.
EXW, not our preferred DAP: we book and pay the freight.
The quality agreement applies: on-time delivery target 95 %, flat fee of EUR 150 per supplier-caused complaint.
Valid from 2024-01-01 to 2026-12-31; extends by 12 months unless terminated with 90 days' notice.
Delivery
Each goods receipt against its order line's requested date. On time = posted between 5 days early and 2 days late (scorecard method); partial deliveries count separately.
Against its own first confirmed dates: 88.9 % on time. Since 2023-10: 71 order lines, 7 rush and 3 changed orders, 1 still open.
Quality
Quality notifications (qn:). Supplier-caused complaints are recharged at the €150 flat fee; an 8D report is due within 60 days.
Median 53 days to close; 3 closed after 60 days; 0 open, of which 0 overdue. 6 parts returned in total; €1,050 recharged.
| Notification | Part | Defect | Qty | Cause | 8D |
|---|---|---|---|---|---|
| qn:20004890 2026-04-19 | part:320011 Pump shaft HN 32 mm | wrong material certificate | 1 | supplier | 89 d |
| qn:20004763 2025-12-13 | part:320011 Pump shaft HN 32 mm | surface damage | 1 | supplier | 53 d |
| qn:20004749 2025-11-25 | part:320011 Pump shaft HN 32 mm | dimension out of tolerance | 1 | supplier | 53 d |
| qn:20004632 2025-08-22 | part:320011 Pump shaft HN 32 mm | dimension out of tolerance | 1 | supplier | 52 d |
| qn:20004611 2025-07-18 | part:320011 Pump shaft HN 32 mm | burr / sharp edge | 1 | supplier | 39 d |
| qn:20004490 2025-03-18 | part:320011 Pump shaft HN 32 mm | missing marking | 1 | supplier | 68 d |
| qn:20004465 2025-03-03 | part:320011 Pump shaft HN 32 mm | coating defect | 1 | supplier | 34 d |
| qn:20004407 2025-01-11 | part:320011 Pump shaft HN 32 mm | missing marking | 1 | supplier | 47 d |
| qn:20004234 2024-07-26 | part:320011 Pump shaft HN 32 mm | porosity | 1 | not supplier | 41 d |
| qn:20004056 2024-01-18 | part:320011 Pump shaft HN 32 mm | dimension out of tolerance | 1 | supplier | 98 d |
The 12 most recent notifications. The scorecards on the supplier page give the rolling ppm.
Our payments
Invoices (inv:) against their due date. This is our side of the relationship: suppliers notice when we pay late.
Invoice terms: 30 days. 2 invoices unpaid at the data date, 1 already past due.
Cash discount: 3 % within 10 days. Taken 39 times, 7 of them after the discount period (€2,085).
By fiscal year
October to September.
| Year | Invoiced | Invoices | Paid late | Avg days late | Complaints | Recharged |
|---|---|---|---|---|---|---|
| FY2024 | €191,910 | 22 | 40.9 % | -6.9 | 1 | €150 |
| FY2025 | €232,832 | 24 | 45.8 % | -2.7 | 5 | €600 |
| FY2026 | €235,354 | 28 | 53.6 % | -1.5 | 3 | €300 |