Deal anatomy · P05 RFQ: pump shaft for the new HX series

engine v1.5b · session 99d24a103a1930cc · goal Leverage

Accepted offer:70250-2 from sup:70250 Drehteile Fuchsreiter GmbH.

The score

brief/api.md: score = clip((C_open − C_deal) ÷ (C_open − C_best), 0, 1). C is total cost over the contract horizon.

(€305,545 − €251,831) ÷ (€305,545 − €223,424) = 65

Opening offer €305,545 · best possible €223,424 · our alternative none (no deal scores 0). Each euro of C saved is worth 0.0012 points.

Where the deal's total cost comes from

Each term recomputed from the case file and the closing terms, the way the kit's cost.py does, and checked against the arena's breakdown for this run.

TermThis deal, worked out€Arena
Price
units before the new price × current price + (committed − those units) × unit price
8,400 units × €29.61 = €248,724€248,724✓
Uncovered need
(need × horizon − covered) × fallback price; covered = min(volume, need) × years
(8,400 − 8,400) × €36.39 = €0€0✓
Fallback risk
uncovered need × fallback risk %
€0 × 3 % = €0€0✓
Payment terms
spend × our interest rate × (reference payment days − payment days) ÷ 360
€248,724 × 8 % × (60 − 14) ÷ 360 = €2,543€2,543✓
Freight
committed units × freight per unit for the Incoterm
8,400 × €0.00 (DAP) = €0€0✓
Late delivery
late cost per day × max(0, lead time − lead time we need)
€200.00 × max(0, 28 − 35) = €0€0✓
Quality
committed × ppm ÷ 1,000,000 × (cost per defect − chargeback)
8,400 × 600 ÷ 1,000,000 × (€112.00 − €0.00) = €564€564✓
Tooling
tooling paid once
€0€0✓
Index clause
spend at the new price × material share × max(0, |expected move| − deadband) × sign
no index clause = €0€0✓
Index risk
spend at the new price × material share × index risk %
no index clause = €0€0✓
Supplier health
€ per margin point × soft(sustainable margin − supplier margin) × years (stabilise and secure-supply only)
€0: only charged in stabilise and secure-supply cases€0✓
C of the dealsum of the terms€251,831€251,831

Horizon covered: 2 years · committed 8,400 units · covered 8,400 of 8,400 needed.

The closing terms and where each came from

A deal closes on our accepted sheet for the negotiable fields, the case's fixed terms, and the supplier's standard terms (its quote PDF) for anything left out.

Payment terms14 daysnegotiated
Lead time28 daysnegotiated
Volume / year4,200 pcfixed by the case
Contract length24 monthsfixed by the case
Effective from2027-01-01fixed by the case
Index clausenonefixed by the case
IncotermDAPfixed by the case
Tooling€0.00fixed by the case
Defect commitment600 ppmsupplier's standard terms
Chargeback / complaint€0.00supplier's standard terms
Unit price€29.61negotiated

What each lever was worth

Total cost C with one negotiable term set to each allowed option and everything else as closed (supplier-health charge held). This shows the buyer's side only: the supplier prices each option too.

Payment terms
14 daysdeal€251,831—
30 days€250,947−€884
45 days€250,118−€1,713
60 days€249,288−€2,543
90 days€247,630−€4,201★
Lead time
28 daysdeal€251,831—★
35 days€251,831—★
42 days€253,231+€1,400
56 days€256,031+€4,200

★ cheapest for us at the deal's price. Whether the supplier accepts it at that price is the negotiation.